BID OPENING

April 12, 2005

File # 19,#28

Milton, Florida

 

Present:  Procurement Officer, Office Assistant II, Brad Stevens representing Rast Construction, Larry Morgan representing Morgan Contracting, Inc., Chris W. Very representing Cajun Constructors, Inc., and Joe Klaus representing CH2M Hill.  The meeting took place at 10:00 a.m.

 

The purpose of the meeting was to open bids for Navarre Beach Wastewater Treatment Upgrade, and Animal Control Units. Bids were received from the following:

 

  Navarre Beach Wastewater Treatment Upgrade:

1. Morgan Contracting, Inc.                              $5,790,000.00

2. Rast Construction, Inc.                                 $6,780,000.00

3. Cajun Constructors, Inc.                               $6,818,000.00

 

  Animal Control Units:

1. Jones Trailer Co.                                          $13,458.00  each

2. Deerskin Mfg., Inc.                                       $16,612.25  each